// NEED THIS

Expect lane closures north of Harris Beach

The Curry Coastal Pilot

ODOT and prime contractor Legacy Contracting plan to begin construction on the Harris Beach Multiuse Path project this week.

According to the contractor's latest schedule, there will be a continuation of lane closures with flaggers today (July 16) for the placement of temporary barriers. Motorists should expect intermittent lane closures the next week and a half.

Starting Monday, Legacy plans to begin driving pile south of Dawson Road along the west side of U.S. 101. This will be a noisy process that will take several weeks. All pile-driving will be done during daylight hours, from 8 a.m. to 6 p.m. U.S. 101 will be limited to a single-lane of traffic for most of August. Flaggers will provide traffic control.

The city will provide more information as it becomes available.

13771750
The Curry Coastal Pilot
This image is copyrighted.

Brooking's autos, jobs, real estate and merchandise.

Ads appear Online and in Print

View Classifieds

Connect with The Curry Coastal Pilot


Curry Pilot Newsstand

Friday September 30, 2016

Read digital interactive editions of our publications

Read Today's Edition Take A Tour
View All Publications